NOTAM: Lopez Airport Construction Schedule

Here is the schedule for Lopez.  This schedule is tentative and may change due to weather conditions and construction needs.

June 13 to June 20                           Runway 34 threshold relocated 568’, runway length available 2,340’

June 23 to June 24                           Full runway length available for the week end

June 21 & 22 and
June 25 to June 29,                          The airport is closed

June 30 to July 8                               Full runway length available

July 9 to July 22                                Runway 16 threshold relocated 700’, runway length available 2,210’

July 23 to August 7                           Runway 16 threshold relocated 990 ‘, runway length available 1,920’

There will also be a 3 day closure for remarking the runway and a possible fog seal.

Significant portions of the parallel taxiway and connecting taxiways will be closed during construction of this project which will require aircraft to back taxi on the runway.

About Bryan Hoyer

Inventor, Entrepreneur and Adventurer
This entry was posted in Uncategorized. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

w

Connecting to %s