I wanted to update you on the schedule for the sewer line that will be going through airport property and across the north end of taxiway Bravo.

At the pre-construction meeting I was advised that construction will begin at the hospital site on May 14th and cross Franklin Drive, then move up the hill behind Island Air along the grass. They will be installing pipe and manholes along this route.

Beginning next week (May 21-23) they will cut the taxiway just south of Ernie’s café which will require tenants in the northern portion of the airport to use the transient parking entrance to the runway. (I will be happy to assign any tenant a spot south of the construction area if you would prefer.) This portion of the construction is scheduled for 3 days and the taxiway should be back open late on the 23rd.

From the 24th -28th, construction will continue along the North side of Aeronautical Services and cross Vehicle Gate 4 which will mean those folks who use this entrance will have to use another route. Hopefully, all will be complete by the end of the month or early in June. Please pass along this message to  your airport friends. Thank you so much for your patience and as always, if you have any questions, please give me a call.

Regards,

Dave

David M. Ryan, Airport Manager
Friday Harbor Airport
P.O. Box 889
Friday Harbor, WA 98250
(360) 378-4724
daver@portfridayharbor.org

Advertisements

About Bryan Hoyer

Inventor, Entrepreneur and Adventurer
This entry was posted in Uncategorized. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s